In compliance with the instruction from PT. Karya Teknik Group, Jakarta, with
reference to their email message dated March 03, 2014, our Surveyor from Klang
Office did attend on board the vessels:
TB. “KARYA
PACIFIC 11” and BG. “PACIFIC STAR 18”
on
March 03-07, 2014 whilst they were lying afloat and berthing at Sritama Sdn Bhd
Jetty, Klang - Malaysia, in order to conduct a “Towing & Lashing Survey”
The
TB. KARYA PACIFIC 11 & BG. PACIFIC STAR 18 was surveyed on March 05, 2014
up to March 07, 2014. The survey was conducted in order to check the cargo
condition, tug boat and barge condition which generally was found in satisfactory
condition. The cargo stowage, lashing
and towing arrangements are sufficient and the vessels are fit to proceed with
their voyage from Sritama Sdn Bhd Port, Klang, Malaysia to Tanjung Karas,
Samarinda, Kalimantan, Indonesia.
Towing and Lashing Survey Tongkang Pacific Star 18 |
VESSEL’S
PARTICULARS
Tug's
Particulars
·
Name of Tug Boat : TB. KARYA PACIFIC 11
·
Type
of Vessel : Steel
Tug
- Call Sign : YDA 4971
- Port of Registry : Tanjung Priok
- Flag : Indonesia
- Classification : BKI
- Gross Tonnage : 207
- Net Tonnage : 63
- Dimensions : 27.00 M (L.O.A)
- 8.20 M (Breadth Moulded)
- 4.00 M (Depth Moulded)
- Built : 2011/Batam, Indonesia
- Owner Name : PT. Karya Pacific Shipping
- Main Engine : 2 x Yanmar Marine Diesel Engine
Model
12LAKM-STE2 (1100 HP/1850 RPM)
- Local Agent : Titimas Shipping Sdn Bhd, Malaysia
- Name of Master : Capt. Muhammad Azmi
Barge's
Particulars
§ Name
of Barge : BG. PACIFIC STAR 18
§ Type of Vessel : Flat Deck Barge
§ Port of Registry : Tanjung Priok
§ Flag : Indonesia
§ Classification : BKI
§ Gross
Tonnage : 3,245
§ Net
Tonnage :
974
§ Dimensions : 91.44 M (L.O.A) / 87.78 M (LBP)
§ 25.60
M (Breadth Moulded)
§ 5.49 M (Depth Moulded)
§ Built : 2012/Batam, Indonesia
§ Owner Name : PT.
Karya Pacific Shipping
§ Local Agent : Titimas
Shipping Sdn Bhd, Malaysia
CARGO’S
PARTICULARS
Packing List No. 13684
§ Description
of goods : Completed Set of
Machineries and Equipment
for
Crude Palm Oil Mill
§
Total : 542 packages
§ Shipper
: Cedar Engineering Sdn Bhd
Lot 803 Jalan Subang 5, Taman Perindustrian
Subang
47610 Subang Jaya, Selangor, Darul Ehsan,
Malaysia
Phone : (603) 56349097
Fax : (603) 56349098
§ Consignee
: PT. Karya Teknik Plantation
Desa Sumber Sari, Kecamatan Sebulu
Kalimantan Timur, Indonesia
§ Port of Loading : Sri Tama Port, Klang, Malaysia
§ Port
of Discharge : Tanjung Karas,
Samarinda, Kalimantan, Indonesia
ATTENDING
PARTIES
·
Capt. Muhammad Azmi : Master of TB. "KARYA
PACIFIC 11”
·
Mr. Mulham Bin Haji Hamid : Chief Officer of TB. KARYA PACIFIC 11
·
Mr. Warno :
Chief Engineer of TB. KARYA PACIFIC 11
·
Mr. Aseng : Representative of Sritama Sdn Bhd
·
Mr. Lee Hatta : Representative of Titimas Shipping Sdn Bhd
·
Mr. Dilip : Loading Master from Sritama Sdn Bhd
·
Mr. Ruly Abdillah : Surveyor from
PT. Carsurin, Batam
FINDINGS
Condition
of the Tugboat
The TB. KARYA PACIFIC 11
was surveyed at Sritama Sdn Bhd Port on March 05, 2014. The Condition Survey
was carried out of the external only. All structures and plating were counted
from fore to aft, port to starboard, unless otherwise stated.
The
tug boat “KARYA PACIFIC 11” is a steel tug of all steel
welded construction with 2 units of Yanmar Diesel Engine Type of 12LAKM-STE2
1100 HP @1840 Rpm,
moderate displacement, rake bow, straight side and angular stern. Her main deck
is surmounted with a single course deck house with a set of maneuvering
controls facing forward.
Navigation
and communication devices such as Radar, GPS, Compass, SSB Radio and marine VHF were found in good condition
and working order.
Life saving appliances and fire
fighting equipments such as life rafts, life jackets, life buoys and portable
fire extinguisher were available on board and ready for use in such of
emergency situation.
Main engine, auxiliary engine and
other machineries were not tested due to their efficiency however it was
reportedly by Chief Engineer all machineries were noted in working order,
except generator starboard engine still under maintained when we surveyed.
Condition of the Barge
The BG. PACIFIC STAR 18was surveyed
at Sritama Jetty on March 05, 2014. The barge “PACIFIC STAR 18” is a steel
barge of all steel welded constructions with swim ends, provided with cargo
stanchions and sideboard at port and starboard side respectively and found in
satisfactory condition.
Her
main deck was found satisfactory condition. Ship side external and internally
plating was considered to be satisfactory condition.
Towing
brackets with smith pad eyes was provided at forward and found in good
condition while the emergency towing was also noted in an apparent sound
condition.
One
unit of hand winch with anchor was available at fwd side and found in
operational condition.
GENERAL
INFORMATION
March 03, 2014
§ Vessel arrived at Sritama Jetty
: March 01, 2014 at 17.00 hrs
§ First line ashore :
March 01, 2014 at 17.15 hrs
§ Vessel berthed : March 01, 2014 at 18.00 hrs
March 03, 2014
§ Commenced Loading : March 03, 2014 at 08.00 hrs
§ Stevedore Break time :
March 03, 2014 at 12.00 Hrs
§ Resumed Loading : March 03, 2014 at 13.10 Hrs
§ Stop loading Stevedore break time : March
03, 2014 at 18.00 hrs
March 04, 2014
§ Resumed Loading : March 04, 2014 at 08.00 Hrs
§ Stevedore Break time :
March 04, 2014 at 12.00 Hrs
§ Resumed Loading : March 04, 2014 at 13.00 Hrs
§ Stop loading Stevedore break time : March
04, 2014 at 18.00 hrs
March
05, 2014
§ Resumed Loading : March 05, 2014 at 08.00 Hrs
§ Stevedore Break time :
March 05, 2014 at 12.00 Hrs
§ Resumed Loading :
March 05, 2014 at 13.05 Hrs
§ Stop loading Stevedore break time : March
05, 2014 at 18.00 hrs
March
06, 2014
§ Resumed Loading : March 06, 2014 at 08.00 Hrs
§ Stevedore Break time :
March 06, 2014 at 12.00 Hrs
§ Resumed Loading :
March 06, 2014 at 14.00 Hrs
§ Completed loading all cargo
: March 06, 2014 at 18.00 hrs
March
07, 2014
§ Commenced Lashing : March
07, 2014 at 08.00 Hrs
§ Completed Lashing :
March 07, 2014 at 17.00 Hrs
§ Final inspection for towing & lashing
: March 07, 2014 at 18.00 hrs
CARGO STOWAGE AND SECURING
Cargo’s Stowage
At the time before the cargo stowed on board the barge
we noted that the cargo of Completed set of Machineries and equipments for
Crude Palm Oil Mill were properly not covered by tarpaulin and stowed at the
open yard of Sritama Sdn Bhd, Malaysia premises.
Loading the cargo by loader for
inland transportation from Sritama Premises to ship side barge Pacific Star 18 was
carried out by means of shore Loader with capacity 50 Tons SWL. The cargo
concerned was carefully handled in order to prevent any risk of damage and then
properly stowed on the loaders in lengthwise position. During inland voyage transportation
from Sritama premises to ship side distance about 1 km, no damage was reported.
Loading the cargo on to the barge’s
deck was carried out by means of shore crawler crane 2 (two) unit PH Kobelco
type with capacity 45 Tons SWL including spreader bar, wire rope and shackles.
The cargo concerned was carefully handled in order to prevent any risk of
damage and then properly stowed on the barge’s deck in various kind, athwart
and lengthwise position.
Cargo
Lashing / Securing
Completed set
of Machineries and equipments for Crude Palm Oil Mill
were lashed/secured as follows:
All cargoes were properly stowage on the
barge deck, there are not lashing applied against cargo on barge deck, the lashing
only applied on the top of cargo from sideboard port side to sideboard
starboard side, each sideboard side was lashed/secured at 8 points by using
wire lashing of 5/8” dia, wire clips, shackles, turnbuckles and steel pad eyes.
Each lashing point was tightened by turnbuckles to the available pad eyes.
TOWING
ARRANGEMENT
Prior to departure, the
towing arrangement was inspected and found as follows:
A tow of the main tow line
of 200 m of 10” circ. of polypropylene rope was connected to the towing hook on
the tug and another one end connected to the 2nd towing line of 60 m
of 10” circ. of Polypropylene rope by using shackle of 35 Tons SWL and one end
of 2nd towing line was then connected to a pair of 10” circ. Of
Polypropylene rope of 25 m in length by using shackle of 35 Tons SWL and
finally the chain wire bridles end to be connected to a pair of smith pad eyes
on board the barge.
VOYAGE
PARTICULARS
§
Port
of departure : Sritama Sdn Bhd Port, Klang, Malaysia
§ Destination : Tanjung Karas, Samarinda, Kalimanatan Timur
§ Distance
between ports : About 1100 nautical miles
§ Towing
speed : 6 knots
- Schedule route : Klang – Selat Malaka - Selat Durian – Selat Berhala –
Selat Bangka – Laut Jawa – Selat Makassar –
Muara
Pagah – Tanjung Karas,
Samarinda
- March 08, 2014 at 09.00 hrs LT : E.T.D from Sritama Sdn Bhd Klang
- March 16, 2014 AM : E.T.A Tanjung Karas, Samarinda,Indonesia
- Voyage Duration : 8 days
DEPARTURE CONDITION
The
Tug Boat
Consumable Remaining on board Daily Consumption
H.S.D 34,000
Liter 4,300 Liter
Fresh Water 10,000 Liter 2,000 Liter
Provision: not sufficient for the
purpose voyage should be bunkering
The
Barge draft Fore: 1.50 M and Aft: 2.00 M
SURVEYOR’S NOTES
§
Bunker
remaining on board not sufficient for the purpose voyage should be get
bunkering on board prior sailing.
§
All
recommendation made on preparation for the contemplated voyage have been
completed with our satisfaction except the attached “Recommendation to the
Master” which to be complied enroute as well as tug/barge’s condition.
§
We
are of the opinion that stowage, lashing/securing of the cargo and towing
arrangements are sufficient and the carriers are fit to proceed in
transportation for the contemplated voyage. Should there any alternation to the
carrier or other arrangement occurs, this certificate become invalid pending a